Valencian planning law: licences, illegal builds and rural plots
The consolidated Valencian Law on Territorial Planning, Urbanism and Landscape (TRLOTUP), the provisions a buyer of a villa, a country house or a plot needs: what requires a licence and what a responsible declaration, including occupation of a home; the ban on rural subdivisions and on selling undivided shares for separate use; the fifteen-year limit for ordering demolition and the land where there is no limit at all; why enforcement follows the property into the buyer’s hands; the regularisation of older rural housing clusters; and fines up to 1.5 million euros.
A rural house: the questions that matter
Was it built with a licence? If not, the council has fifteen years from completion to order restoration on most land (article 255.1) — but on non-developable (rural) land, green zones, roads and public domain there is no time limit at all (article 255.5). Passing the fifteen years does not legalise the building, and no extension or consolidation works are then allowed (article 256). The measures bind whoever owns the property, including a later buyer (article 250.2), and the opening of a file is noted in the Land Registry (article 250.3). Older unlicensed houses in rural clusters can only be legalised through a minimisation plan, and only if completed before 20 August 2014 (article 228.3). Ask the town hall for its written planning information on the plot, which it must give within a month (article 246.4).
Book II, Title IV. Rural land and developable land without a programme (selected)
Chapter III. Minimising territorial impact on non-developable land (selected)
Article 228. Actions to minimise the territorial impact generated by housing clusters on non-developable land
1. The structural general plan, or any planning instrument capable of establishing the structural planning, may delimit as a planning zone on non-developable land consolidated housing clusters that must minimise their territorial impact, whose establishment took place outside the formalised urbanisation and building processes.
2. For the purposes of the delimitation referred to in the preceding paragraph, consolidated housing clusters are groupings of dwellings established in areas of non-developable land. For the purposes of minimising territorial impacts, a grouping of dwellings on non-developable land exists wherever there is a density equal to or greater than three dwellings per hectare, without prejudice to groups of lower density being considered as such where appropriate by reason of proximity, infrastructure and territorial conditions.
3. Only buildings fully completed before 20 August 2014 may legalise the works and the residential use through their inclusion within the scope of the instruments regulated in this chapter. This is regardless of their legal and administrative situation, and saving the content of the court judgments issued on them, which must be complied with in accordance with the enforcement decisions issued by the courts.
The application to start the strategic environmental and territorial assessment of any of the impact minimisation instruments regulated in this chapter entails the suspension of the processing of files to restore planning legality, or of the enforcement of the decisions issued, on works that may be covered by them. The limitation or lapse periods of the actions or procedures in enforcement or processing are likewise suspended.
If the instrument is not approved, the possibility of legalising the buildings through the instruments regulated in this chapter lapses, and the appropriate orders must be issued and enforced in accordance with articles 250 et seq. of this consolidated text.
4. To legalise, through the plan, buildings located on land enjoying any type of protection for its special environmental values, or land affected by specific use limitations arising from the application of sectoral rules on mines, coasts, water, flood risk or infrastructure, or by the existence of activities lawfully established or in the process of legalisation, a prior binding report must be issued by the administration with the affected powers.
5. Where the consolidated housing cluster or isolated dwellings subject to the minimisation of territorial impact are located on forest land or land adjoining it, efforts shall be made to carry out the measures that forest fire prevention legislation establishes for new developments, buildings and uses.
If these measures are not carried out in the legalisation project, the public administration shall be exempt from liability in the event of material damage as a result of a fire.
Where the consolidated housing cluster subject to the minimisation of territorial impact is located in a flood-prone area, and for existing buildings, the competent administrations shall require the adoption of measures to reduce vulnerability and for self-protection, all in accordance with Law 17/2015 of 9 July on the National Civil Protection System and the Territorial Action Plan on the prevention of flood risk in the Valencian Community.
In the two preceding cases, the promoter must sign a responsible declaration stating clearly that it knows and accepts the existing risk and the applicable civil protection measures, undertaking to pass that information on to any persons affected, regardless of the complementary measures it considers appropriate to adopt for their protection. This responsible declaration must be included, where applicable, in the documentation of the works licence or legalisation file.
The responsible declaration of first occupation shall be accompanied, where applicable, by a certificate from the land registry evidencing that there is a registry entry indicating that the construction is in a forest area without having carried out the forest fire prevention measures, or that it is in a flood-prone area.
Article 231. Effects of the territorial impact minimisation action
1. After approval of the special plan or the minimisation programme, the existing plots shall be indivisible, except for the aggregation of the segregated part to an adjoining one, if both meet the established minimum plot.
2. The existing dwellings, once the infrastructure programmed for minimising territorial impact has been completed, may be legalised by applying for the required legalisation works licence in order to evidence that the property complies with the special plan of the territorial impact minimisation action. In these cases the requirements for single-family dwellings regulated in article 211.1.b of this consolidated text do not apply.
3. No works or use licence entailing an extension of the buildability already acquired may be granted for these buildings, not even with removable provisional elements. The plan and the minimisation licence may regulate the future authorisation of interior reform works or the execution of small auxiliary elements that do not increase buildability and do not entail a negative alteration of the landscape and environmental effects achieved with the minimisation. The grant of these licences must have a prior binding report from the department responsible for planning and landscape.
4. Unbuilt plots must remain outside the scope of the action. If any is included, it shall remain unbuilt in its agricultural or forestry use or be used as open space, and shall in any event be exempt from payment of urbanisation costs.
5. In the event of breach of the obligation indicated in article 190.1 and related articles of this consolidated text, the town council may, after a twenty-day hearing for the interested persons, issue the execution orders necessary for its fulfilment. The orders shall be subject to the regime established in articles 192 and related articles of this consolidated text.
6. Six months after issuing the orders indicated, if the building has not been adapted to the provisions of this article, the town council may impose coercive fines, on the terms provided for in article 260.1.a of this consolidated text and, where applicable, the works corresponding to the obligation established in article 190.1 of this consolidated text may be carried out subsidiarily by the town council.
Book III. Planning discipline
Chapter I. Administrative control of planning legality (selected)
Section I. Licences (selected)
Article 232. Acts subject to licence
The following acts of use, transformation and building of land, subsoil and airspace are subject to a planning licence, on the terms of this consolidated text and without prejudice to the other authorisations appropriate under the applicable legislation:
a) Earth movements, levelling, subdivisions, segregations or other acts dividing properties on any class of land, where they do not form part of a reparcelling project.
b) Works of building, construction or installation of new buildings.
c) The placement of prefabricated houses and similar installations, whether provisional or permanent.
d) The felling of tree masses or shrub vegetation on land incorporated into urban transformation processes and, in any event, where the felling arises from the legislation protecting the public domain.
e) Works and uses that must be carried out on a provisional basis.
f) Interventions on buildings, properties and areas that are protected or listed as heritage, having heritage significance in accordance with the rules protecting cultural heritage.
g) The extraction of aggregates and the operation of quarries, except as provided in article 234.1.b of this consolidated text.
h) The accumulation of waste and the deposit of materials foreign to the characteristics of the natural landscape.
i) The construction of dams, ponds, works defending and correcting public watercourses, public or private roads and, in general, any type of works or uses affecting the configuration of the territory.
Article 233. Actions subject to responsible declaration
1. The following are subject to responsible declaration, on the terms of article 241 of this consolidated text:
a) The installation of electricity, telephone or similar lines, the commissioning of medium-voltage electricity transformer stations, provided that they have been previously authorised, and the placement of antennas or communication devices of any kind and the repair of underground pipes, only on urban land and provided that it does not affect the public domain, protected buildings or protected surroundings of properties declared assets of cultural interest or of local relevance, or other areas of archaeological monitoring.
b) Modification or reform works affecting the structure, without entailing the replacement or substitution of main structural elements, or the exterior and interior appearance of constructions, buildings and installations, that are not subject to licence under article 232 of this consolidated text.
c) Works of mere reform not entailing structural alteration of the building, nor affecting listed elements or elements in the process of listing, and maintenance works on the building that do not require scaffolding to be placed on the public highway.
d) Interventions on buildings, properties and areas that are protected or listed as heritage, lacking heritage significance in accordance with the rules protecting cultural heritage.
e) The raising and repair of non-structural masonry or brick walls, and the fencing of plots, regardless of the construction system chosen, that are not subject to licence under article 232 of this consolidated text.
f) The first occupation of buildings and installations, once their construction is completed, in accordance with the legislation in force on the organisation and quality of building, as well as the second and subsequent acts of occupation of dwellings.
2. The following actions are subject to responsible declaration, in accordance with the preceding paragraph and provided that they are accompanied by a certificate issued by an administrative certification body or a professional association, on the terms established in the fourth additional provision of this consolidated text:
a) Modification or reform works affecting the structure of constructions, buildings and installations of all kinds, whatever their use.
b) The demolition of constructions.
c) The modification of the use of constructions, buildings and installations, and the use of the airspace over them.
d) The raising of masonry walls and enclosures, in the cases and aesthetic conditions required by the plans’ ordinances regulating the harmony of construction with its surroundings.
e) The execution of works and installations affecting the subsoil, except those included in article 232.
f) The opening of tracks, and their modification or paving.
g) The placement of advertising signs and hoardings visible from the public highway.
h) All actions not included in articles 232 or 234 or in paragraph 1 of this article.
The reform or rehabilitation of a facade, or any complementary works included in paragraph 1 of this article, requiring the installation of scaffolding on public domain shall be processed as a responsible declaration. However, the temporary occupation of public land or airspace for the installation of scaffolding or temporary auxiliary installations until the works are completed shall require a licence for occupation or equivalent legal title, to be processed by the municipal department responsible for the public domain.
Article 241. Responsible declaration for reform works on buildings, constructions or installations and minor works
1. The responsible declaration for the cases in article 233 of this consolidated text shall conform to the legislation in force on the common administrative procedure.
2. The responsible declaration shall be accompanied by the following additional documents:
a) Evidence of the identity of the promoter and of the other building agents.
b) Graphic and written description of the action and its physical location, and a project signed by competent technical staff where the nature of the works so requires, with a brief report issued by its author evidencing compliance with the applicable rules.
c) Additional documentation required by environmental rules, where appropriate.
d) Indication of when the works are intended to start and measures relating to the removal of rubble and use of the public highway.
3. The promoter, once it has declared under its responsibility that it meets all the requirements to carry out the action concerned, and has filed that declaration with the town council or competent local entity together with all the required documents, shall be entitled to start immediately, without prejudice to the municipal powers to verify or inspect the requirements enabling the exercise of the right and the conformity of what is executed with the content of the declaration.
4. The filing of the responsible declaration, made on the terms provided for in this provision, shall have the effects that the applicable rules attribute to the grant of the municipal licence and may be relied on both before the administration and before any other natural or legal person, public or private.
5. Any essential inaccuracy, falsehood or omission in any data, statement or document accompanying or included in the responsible declaration, or failure to file it with the competent administration, shall make it impossible to start the works or carry out the corresponding acts from the moment those facts become known, without prejudice to any liabilities that may arise. The administrative decision declaring such circumstances may determine the obligation of the interested party to restore the legal situation to that existing before the recognition or exercise of the right or the start of the corresponding activity; all of this without prejudice to the processing, where applicable, of the corresponding penalty procedure.
6. The planning legislation and planning instruments applicable to responsible declarations shall be those in force at the time of their filing. Any technical and legal reports issued by the municipal administration for the issue of the decision referred to in the preceding paragraph shall have the scope established in article 239 of this legal text.
Article 244. Lapse of licences
1. All licences shall be granted for a fixed period both to start, complete and not interrupt the works, in accordance with article 188 of this consolidated text, except those relating to uses, which shall have indefinite validity without prejudice to the legal obligation to adapt to the rules regulating them at any time.
2. Municipalities may grant extensions of the periods of licences for a new period not exceeding that initially agreed, provided that the licence conforms to the planning in force at the time the extension is granted.
3. The lapse of the licence shall be declared after hearing the interested party.
4. The declaration of lapse shall extinguish the licence, and the works may not be started or continued unless a new licence conforming to the planning in force is applied for and obtained. If the works or installation remain unfinished or halted after the declaration of lapse, an execution order may be issued to complete the work essential to ensure the safety, health and public appearance of the interrupted works. One year after the declaration of lapse, the unfinished works may be made subject to the compulsory building regime.
Article 245. Obligations of service supply companies
1. To contract their services, water, electricity, gas, telephone and telecommunications supply companies shall require the holder of the works or activity to evidence that the corresponding planning and environmental intervention instruments have been obtained.
2. Orders for the suspension, stoppage or demolition of any works, uses or buildings shall be notified to the companies supplying or providing the services specified in the preceding paragraph, so that they suspend the corresponding supplies within ten days.
3. The suspension of supplies may only be lifted once the respective works, uses or buildings have been legalised, by express notification to that effect from the administration to the supply companies.
4. Companies supplying or providing energy, water, gas, telephone and other services must:
a) Refrain from extending networks and providing services or supplies to land, buildings, installations, works or constructions unless it is evidenced to them that these have the corresponding planning and environmental intervention instruments for the actual use to which they are put, a copy of which they shall require from those requesting the services and keep under their responsibility.
b) Comply within ten days of receipt with the orders to suspend supply given by the planning administration in relation to those activities and works whose stoppage it has ordered, within the procedure for the protection and restoration of planning legality.
c) Duly comply, as regards the services they provide, with the requests for information addressed to them by the planning authority.
Section II. Planning guarantee certificate
Article 246. Planning guarantee certificate
1. Town councils must issue, at the request of the interested parties and within one month, a planning guarantee certificate for plots capable of building or private use. The certificate shall state the zoning and planning classification and its maximum period of validity shall be one year.
2. The owner of the building plot or plot for which the certificate has been validly issued for the first time shall be entitled, during its validity, if the planning conditions stated in it are not maintained, to have the responsible municipalities make good the financial loss caused by supervening changes in planning, provided that the interested party had no outstanding duties of cession, equidistribution or urbanisation and this was so stated in that certificate.
3. The grant of planning guarantee certificates shall be suspended during the suspension of the grant of licences.
4. Regardless of the preceding paragraphs, town councils are obliged to inform any applicant in writing of the zoning, classification and planning programming of the land, within one month.
Section III. Subdivisions
Article 247. Licences for subdivision or division of land
1. Every subdivision, segregation or division of land shall be subject to a municipal licence, unless the town council declares it unnecessary. A licence shall be unnecessary where:
a) The division or segregation is the result of a reparcelling, expropriation, action programmes, declarations of community interest, public works or services or cession, whether compulsory or voluntary, free or for consideration, to the administration, so that it uses the land resulting from the division for the public use or service to which it is assigned.
b) The division or segregation has been expressly authorised by the municipality on the grant of another planning licence.
c) The purpose of the division or segregation is to divide land with different planning classifications.
2. In accordance with State legislation, notaries and land registries shall require, to authorise and register respectively deeds dividing land, an administrative decision evidencing the grant of the licence or that it is unnecessary, which the former must attest in the document. Notaries and land registries shall also record in the description of the properties their indivisible status, where known to them.
Article 248. Indivisibility of land in the various classes of land
The following are indivisible:
a) Plots so determined in the corresponding planning instrument, in order to constitute independent properties.
b) Plots whose dimensions are equal to or less than those determined as minimum in the planning, unless the resulting lots are acquired simultaneously by the owners of adjoining land in order to regularise boundaries in accordance with the plan.
c) Plots whose dimensions are less than double the area determined as minimum in the planning, unless the excess over that minimum can be segregated for the purpose indicated in the preceding paragraph.
d) Plots that are buildable according to a given relationship between land area and density or volume, where that corresponding to the whole land area has been built, or the remaining parts that are not independently buildable, with the exceptions indicated in the preceding paragraph.
e) Plots located on non-developable land or developable land without programming are not divisible, unless they meet the requirements established in the following article.
Article 249. Subdivisions of rural properties
1. On non-developable land and developable land without an approved programme, a licence authorising any act of division or segregation of properties or land, whatever its purpose, is likewise required, except in the cases where a subdivision licence is unnecessary, after a declaration by the town council, in accordance with article 247 of this consolidated text.
2. In no case may acts of division or segregation of rural properties or land be authorised contrary to the applicable agricultural, forestry or similar rules. Acts of division or segregation may not be authorised contrary to the special minimisation plan regulated in article 229 of this consolidated text.
3. Urban subdivisions may not be authorised on non-developable land or developable land without programming either. The following is prohibited, as being considered an urban subdivision:
a) Any division or segregation of land into two or more lots where its purpose is building or, where applicable, creating the infrastructure required for building to take place, except in the cases of building exceptionally authorisable under this consolidated text.
b) Acts carried out for the same purposes as described in the preceding paragraph which, without division or segregation of the property, subdivide, sell or let undivided shares or percentages of it for the individualised use of various holders, through associations or companies, horizontal divisions, co-ownership, shares or participations, entailing a change in the rural use of the parent property from which they come, in order to evade compliance with this consolidated text.
4. Physical acts of division or segregation of properties may not be authorised where there is a legal presumption that such acts have a planning purpose. A planning purpose is presumed where any of the following circumstances occurs:
a) That infrastructure or services unnecessary for activities related to the use and exploitation of the natural resources of the land by means of normal and ordinary techniques, or of a specifically urban nature, already exist on the land or their installation is planned.
b) That it gives rise to a property with an area smaller than the minimum required by this consolidated text for an isolated family dwelling, unless the number of properties does not increase compared with those existing before, by simultaneous grouping or aggregation of the segregated portion or portions to an adjoining property or properties, provided that none of the properties resulting from such operations is smaller than that classified as indivisible in a previous licence or authorisation and, where applicable, the rules on indivisibility established for planning reasons are complied with. This circumstance shall be considered not to occur where it is evidenced that the purpose of the division or segregation is linked exclusively to agricultural exploitation, in accordance with the applicable agricultural, forestry or similar legislation.
5. If a subdivision is sought in any of the cases provided for in paragraphs 2, 3 and 4 above, the notary, before formalising the subdivision in a public deed, or the land registrar, before making the registry entry, may request a report from the corresponding town council. If three months pass without the report being issued, the subdivision may be formalised in a public deed and registered by the land registrar.
6. Any subdivision contrary to this consolidated text and to the applicable territorial or planning instruments shall be illegal for planning purposes. In no case shall the resulting lots be considered building plots, nor shall building on them be permitted.
7. Municipal licences and the public instruments attesting them, as well as the registry entries made, shall record the indivisible status of the resulting rural properties or the minimum area into which they may be subdivided or segregated, to prevent compliance with this consolidated text from being evaded by successive fragmentation.
8. All authorities within their powers are obliged to detect and prevent the establishment of the physical or legal basis that might distort or cause the transformation of the legal and natural purpose of the rural environment.
Chapter II. Protection of planning legality (selected)
Section I. General provisions
Article 250. Administrative reaction to unlawful action
1. Actions contrary to planning shall give rise to the adoption by the competent administration of the following measures:
a) Those aimed at restoring the legal order infringed and the physical reality altered or transformed as a result of the unlawful action.
b) The initiation of procedures to suspend and annul the administrative acts that may cover the unlawful action.
c) The imposition of penalties on the persons responsible, after the corresponding penalty procedure, without prejudice to any civil or criminal liability.
2. The measures to protect planning legality and restore the disturbed legal order are of an in rem nature and reach third-party acquirers of the properties subject to such measures.
3. The bodies competent to initiate a planning discipline file shall notify the land registry of the decision or agreement initiating the planning discipline procedure for registration.
Article 251. Mandatory nature of the exercise of the power
The adoption of measures to restore the planning order infringed is a power that cannot be waived and must be exercised by the acting administration. Neither the investigation of the penalty file nor the imposition of fines releases the administration from its duty to adopt the measures aimed at restoring the planning order infringed, on the terms established in this consolidated text.
Section II. Works executed without a licence or not in conformity with it
Article 252. Building works without a licence, or not conforming to its terms, in progress
1. Where acts of building or use of land are carried out without a licence or execution order, the mayor and, where applicable, the Valencian Territorial Protection Agency, ex officio or at the request of a party, having verified that they lack planning authorisation, shall order, without further formality, the immediate suspension of the works or the cessation of the use in progress.
The same shall apply where the works are subject to responsible declaration and it has been omitted, or where works subject to licence are intended to be carried out under that regime.
2. The suspension order may be notified, indiscriminately, to the promoter, the owner, the person responsible for the act or, failing them, any person present at the place of execution and connected with the works, and to the public service supply companies so that they suspend supply. The suspension order must also be notified to the land registry for recording by marginal note.
3. Where acts of building or use of land are carried out with a licence or execution order but without conforming to the conditions established in it, the mayor, ex officio or at the request of an interested party, shall address the developer, the builder and the technical management, pointing out the anomalies observed and granting them ten days to make the allegations they consider appropriate. Unjustified failure to reply within that period implies acceptance of the irregularities indicated, so that the mayor shall immediately order the stoppage of the works or the prohibition of the uses, notifying the public service supply companies.
The same rule shall apply to works executed or in progress by responsible declaration, where this is required, that depart from the project attached to that notification or do not fully conform to the planning.
4. If those responsible claim that the licence or execution order conforms to the planning action, they shall be summoned to appear within the following fifteen days at the place where it is being carried out, examining its details jointly with the planning inspectorate and drawing up the corresponding record signed by all those present, in view of which the mayor shall decide as appropriate, allowing the activity to continue or specifying a period for its adaptation to the conditions of the licence, on expiry of which without this occurring the works shall be stopped.
Article 253. Acts in progress without regional planning authorisation where required
1. Where acts of use or building of land are being carried out without regional planning authorisation, where required, or without conforming to its terms, the Valencian Territorial Protection Agency shall order the immediate suspension of those acts.
2. If the actions referred to in the preceding paragraph are being carried out under a municipal licence and conform to its terms, the regional administration may not order the suspension of the acts of execution, but shall, where applicable, challenge the municipal licence, after a request for annulment, or bring a contentious-administrative appeal directly, on the terms established in the local government legislation.
3. The preceding paragraph shall be without prejudice to the provisions of the legislation on natural spaces and cultural heritage in relation to actions that may harm protected natural spaces and assets of cultural interest.
Article 254. Requirement to legalise
1. In cases of works not covered by planning authorisation or not conforming to it, the suspension decision shall require the interested party, within two months of notification of the suspension, to apply for the appropriate licence or planning authorisation or, where applicable, to adapt the works to the planning authorisation granted. This requirement to legalise shall be notified to the land registry on the terms of State legislation.
2. If, after two months, the interested party has not applied for the planning authorisation, or evidenced the legality of the works by responsible declaration where appropriate, the acting administration shall agree the measures to restore legality in the form established in this chapter.
Article 255. Works completed without a licence or not conforming to its terms. Lapse period for the action to order the restoration of planning legality
1. Provided that not more than fifteen years have passed since the full completion of the works or uses of land carried out without a licence or execution order or not conforming to the conditions indicated in it, the mayor and, where applicable, the Valencian Territorial Protection Agency, shall require the owner, within two months, to apply for the appropriate planning authorisation or to adapt the works to the conditions of the licence granted. That lapse period for the administration’s action shall begin to run from the full completion of the works or from when the uses of land concerned cease.
2. For the purposes of this consolidated text, works carried out without a licence or execution order are presumed fully completed when they are ready to serve their intended purpose without the need for any further physical activity relating to the works themselves, or when so recognised ex officio by the authority opening the file, after a report from the corresponding technical services.
3. If the interested party does not apply for the licence or planning authorisation within two months, or if it is refused because its grant would be contrary to the requirements of the planning rules, the procedure in this chapter shall be followed.
4. Notwithstanding the foregoing, if manifest illegality without possible remedy is found in the works, the interested party may be released from applying for a licence, being directly given a one-month hearing to make allegations regarding the opening of a file to restore legality.
5. The fifteen-year period established in paragraph one shall not apply to actions carried out on land classified in the planning as green zones, roads, open spaces or public facility uses, land or buildings belonging to the public domain or included in the General Inventory of the Valencian Cultural Heritage, nor shall it apply on non-developable land. In these cases there shall be no lapse period for the action, as regards the possibility of restoring legality and repairing the assets referred to in this paragraph to their previous state.
6. The lapse period for the administration’s action to restore planning legality that shall apply is that established by the planning law in force on the date of completion of the planning action.
Article 256. Regime of buildings once the period for issuing the order to restore planning legality has passed
The mere passage of the fifteen-year period referred to in the preceding article shall not entail the legalisation of works and constructions carried out without complying with planning legality and, consequently, while the breach of the planning persists, no works of reform, extension or consolidation of what was illegally built may be carried out. However, in order to reduce the negative impact of these constructions and buildings, the acting administration may order the execution of the works necessary so as not to disturb the safety, health and appearance or landscape of the surroundings.
Article 257. Restoration of planning legality
1. The file to restore legality shall end with a decision ordering the adoption, as the case may be, of the following measures:
a) In the case of building works that cannot be legalised, or that can be legalised but have not been legalised in accordance with the procedure established for that purpose, the restoration operations shall consist of the demolition of the illegally executed buildings.
b) In cases of improper demolition, the restoration shall consist of the reconstruction of what was demolished, where appropriate.
c) In the case of illegal subdivisions, the restoration operations shall consist of the regrouping of the plots, which, as the case may be, may be accompanied by the ploughing up of tracks, clearing or dismantling of services, demolition of fences and any others necessary for that purpose.
d) Depending on the action concerned, the restoration operations shall also consist of the execution of all complementary operations necessary to physically return the land, buildings or uses to their state prior to the breach.
e) Where appropriate, the order for the definitive cessation of the activity.
2. In addition to the adoption of the measures in paragraph 1 above, the acting administration shall agree:
a) The cutting off of the supply of water, electricity, gas and telephone. To that end, the acting planning administration shall notify the order to restore legality to the companies or entities supplying electricity, water, gas and telephone, so that they suspend the corresponding supplies within ten days. The suspension of supplies may only be lifted once the respective works, uses or buildings have been legalised, by express notification to that effect from the administration to the supply companies.
b) The disabling of accesses, where appropriate, in accordance with the procedure and guarantees established by the State legislation in force.
c) The entry in the land registry of the administrative decision ordering the restoration of the legality infringed, on the terms established in the registry rules.
d) The notification of the restoration order to the body responsible for the real estate cadastre, for recording.
Chapter III. Planning infringements and penalties (selected)
Section I. General regime of planning infringements and penalties (selected)
Article 264. Concept of infringement
1. Planning infringements are the acts and omissions defined and penalised in this consolidated text.
2. Where the same act may be defined as an infringement in different laws protecting the territory, planning, the landscape, natural resources or historic heritage, only the most severe of the penalties provided shall apply.
Article 265. Very serious, serious and minor infringements
1. Planning infringements are classified as very serious, serious and minor.
2. Very serious infringements are the acts and omissions defined in this consolidated text that constitute a breach of the planning rules relating to the use of land and construction affecting green zones, open spaces, public facilities and amenities or protected non-developable land.
Illegal subdivisions on land pending programming or on which the planning does not authorise urbanisation are likewise very serious infringements.
3. Serious infringements are the acts and omissions defined in this consolidated text that constitute a breach of the rules relating to subdivisions, planning yield, buildability, land use, height, volume, location of buildings and permitted occupation of the area of plots, or building on them in excess of the subjective yield without having met the required planning management conditions.
Culpable breach by the development agent of the commitments assumed with the administration or the owners, except a breach of periods not exceeding one third of that established, is also a serious infringement.
4. Minor infringements are those defined in this consolidated text that are not serious or very serious and, in any event, the execution of works or installations without a licence and execution order where they can be legalised because they conform to the planning rules.
Article 266. Types of penalties
The following penalties may be imposed for the commission of planning infringements:
1. Fine.
2. Disqualification from assuming the status of development agent or building contractor for a period not exceeding four years.
3. Disqualification from being a concessionaire or subcontractor of urbanisation works for a period not exceeding four years.
Article 267. Amount of fines
1. Fines to be imposed for the execution of works or installations without a licence or execution order shall be of variable amount, according to the rules established in the following articles.
2. Other planning infringements shall be penalised:
a) Minor ones, with a fine of three hundred to three thousand euros.
b) Serious ones, with a fine of three thousand and one to thirty thousand euros.
c) Very serious ones, with a fine of thirty thousand and one to one and a half million euros.
3. Where the sum of the penalty imposed and the cost of the actions to restore the assets and situations to their original state is less than the profit obtained from the illegal activity, the amount of the fine shall be increased until it reaches that value. In no case may the planning infringement entail a financial benefit for the offender.
4. In cases where the restoration of the planning order infringed does not require any physical action, the penalty imposed on the offender may not be less than the profit obtained from the illegal activity.
Article 269. Persons responsible
1. All natural or legal persons who commit a planning infringement in their conduct, works or actions, or by failing to comply with their obligations or with the orders addressed to them, shall be responsible.
2. In the case of infringements relating to acts of execution of works and constructions and use of land, the promoter, the construction company and the works management shall be responsible, being considered as such those who meet that definition in the legislation in force on the organisation of building. The person owning the land on which the infringement is committed shall also be considered a promoter, unless proven otherwise.
3. Legal persons shall be penalised for the planning infringements committed by their bodies and agents and shall bear the cost of the measures to repair the planning order breached, without prejudice to any liability of their managers.
4. Companies supplying planning services declared essential shall be responsible for the infringements arising from breach of their obligations defined in this consolidated text.
Article 270. Limitation of infringements
1. Planning infringements shall be time-barred within the following periods:
a) Serious or very serious infringements, after four years.
b) Minor infringements, after one year.
2. The limitation period shall begin to run from the date on which the infringement was committed or, if this is unknown, from the date on which the penalty procedure could have been opened because external signs appeared making it possible to know the facts constituting the infringement.
3. In the case of continuing infringements, the limitation period shall begin from the end of the activity or that of the last act by which the infringement is consummated. A continuing planning infringement is the activity consisting of the repetition of similar acts where all of them have a unity of objective within the same territorial area. Acts of illegal subdivision are in any event presumed to be continuing infringements.
4. The limitation of the infringement is interrupted when the interested person learns of the opening of the corresponding penalty file or of the file to restore planning legality.
Article 271. Limitation of the penalty
1. Serious and very serious penalties are time-barred after four years, and minor ones after one year.
2. The limitation period for penalties shall begin to run from the day following that on which the decision imposing the penalty becomes final.
Section II. Very serious infringements and their penalties (selected)
Article 280. Illegal actions on protected land
Those who carry out on land designated by the planning as green zones, open spaces, public facilities and amenities, or in areas of non-developable land subject to protection, works, installations or actions breaching the rules on use and building shall be penalised with a fine of one hundred to two hundred per cent of the value of the illegal works executed. The amount of the fine shall not be less than three thousand euros.
Article 281. Subdivisions on non-developable land or developable land without programming
1. Those who carry out illegal urban subdivisions on non-developable land or developable land without programming, defined as very serious, or who authorise them, shall be penalised with a fine of twenty to thirty per cent of the sale value of the divided lots.
2. This penalty shall be imposed in its maximum amount if the division carried out harms the specific value that the planning rules protect, where applicable. In any event, the amount of the fine shall never be less than the difference between the initial value and the sale value of the corresponding plot.
Where this sits
The occupation title and the ten-year renewal rule are on the Building Quality Act page; tourist lets and the municipal compatibility report on the Tourism Act page. The Land Registry and the protection of a good-faith purchaser are on our Mortgage Act page.
Related on voixa.es: Valencia: highest income tax, lowest wealth tax; Spain’s 100% property tax for non-EU buyers: what happened.
Nothing here is advice on your own position, and this reading is not the official text. Where the wording matters to a decision, read it against the Spanish original published in the DOGV.