General Regulation of the Andalusian Land Sustainability Act (Decree 550/2022), articles 287 to 296: the nature and purpose of the planning licence, the concept and effects of the responsible declaration and the prior notification, and the types of planning acts subject to municipal control. It then lists the acts that need a planning licence, those that do not, those subject to responsible declaration (with the documents to be attached) and those subject to prior notification, followed by licences and declarations by phases or for parts of a building, and acts promoted by Public Administrations.

Unofficial English translation from the Spanish by Voixa Consultors S.L. Alexander Baranov is responsible for the translation. Source: Decreto 550/2022, de 29 de noviembre, por el que se aprueba el Reglamento General de la Ley 7/2021, de 1 de diciembre, de impulso para la sostenibilidad del territorio de Andalucía, text as published in BOJA no. 232 of 2 December 2022, BOJA ↗. This is the original text, not a consolidated one: later amendments (including those made by Law 5/2025, the Andalusian Housing Act, to articles 83 and 195.4, which are not on these pages) and the correction of errors published in BOJA no. 241 of 2022 are not reflected. Check wording, figures, dates and legal effect against the Spanish original before relying on this reading. Source snapshot: 10 November 2026. This page: Title VI, Chapter II, Sections 1 and 2, articles 287 to 296. Three pages translate articles 287 to 314 on licences and other means of administrative control, and chapter I of Title VIII on irregular buildings in the AFO situation; the rest of the Regulation is not translated.

In this Regulation “the Act” (la Ley) is Law 7/2021 of 1 December on the promotion of the sustainability of the territory of Andalusia (LISTA), and “the Regulation” (el Reglamento) is this General Regulation.

Title VI. Building activity

Chapter II. Means of administrative intervention in building activity

Section 1. General provisions

Article 287. Concept and general rules of planning licences.

1. The planning licence is a regulated act (acto reglado) within the exclusive competence of the municipal administration. Licences may not be granted on the basis of the provisions of future planning instruments, not even conditionally upon the approval of those instruments.

Decisions granting licences may include conditions in order to prevent minor deficiencies in the documentation, or any other remediable defect in relation to the project or application submitted, from preventing the licence being granted. Under no circumstances may the conditions imposed make up for the absence of the concessions, authorisations or reports that are mandatory under sectoral legislation. Licences shall cease to have effect if the conditions to which they were subject are not complied with.

2. Planning licences cannot be granted for acts of construction or building and installation and of use of land, including the subsoil and the airspace, that require other prior administrative authorisations or reports, until those authorisations have been granted or those reports issued, on the terms set out in the Act, in the Regulation and in sectoral legislation.

3. Planning licences must be granted saving the right of ownership and without prejudice to the rights of third parties, and it shall not be necessary to prove title to the properties concerned in order to apply for them, except where granting them may affect assets and rights forming part of the Property of the Public Administrations, whether public domain (demaniales) or private domain (patrimoniales), without prejudice to the authorisations and concessions required under the rules governing the property of the relevant Public Administration.

Article 288. Purpose and scope of the planning licence.

1. The purpose of the planning licence is verification by the municipal administration that the actions of private persons subject to it conform to the territorial and urban planning in force. To that end, municipal intervention shall be directed at verifying, among others, the following aspects:

a) Compliance with the legally required preconditions for carrying out the acts subject to licence.

b) Conformity of the acts subject to licence with the provisions laid down in the territorial and urban planning instruments in force. For this purpose, compliance with at least the following provisions shall be verified:

1st Conditions of plotting or division affecting the property, including the various forms of horizontal property.

2nd Planning uses, densities and building type.

3rd Alignments and grade levels (rasantes).

4th Buildability, building height, permitted site coverage, position, distance from boundaries and between buildings, buildable depth and setbacks.

5th Public or private facilities and amenities provided for the plot or building site (solar).

6th Municipal building and urbanisation by-laws.

c) The impact of the proposed action on the degree of protection of the assets and spaces included in the Catalogues.

d) The existence of the urban services necessary for the building to be put to its intended use.

2. On the terms provided for in sectoral rules, municipal action on the occasion of granting the planning licence shall extend to examining compliance with those provisions whose competence is expressly attributed to town councils, without prejudice to the administrative authorisations or reports that the applicable legislation requires before the licence.

Article 289. Concept and general rules of responsible declarations and prior notifications.

1. The responsible declaration, for the purposes of the Act and of the Regulation, is the document signed by an interested person in which that person states, under their own responsibility, that they meet the requirements laid down in the rules in force to obtain recognition of a right or power or to exercise it, that they hold the documentation evidencing this, submitting it when so required by the Act and the Regulation or, where applicable, making it available to the Administration when requested, and that they undertake to continue to comply with the above obligations for the period of time inherent to that recognition or exercise.

2. The prior notification, for the purposes of the Act and of the Regulation, is the document by which the interested person brings to the attention of the competent Public Administration their identification data or any other data relevant to the start of an action or the exercise of a right.

3. Submission of a responsible declaration that meets the requirements laid down in the Regulation entitles the person, as an enabling precondition (presupuesto habilitante), to carry out the intended action from the day of its submission, provided that it is accompanied by the documentation required under the legislation in force, and without prejudice to the powers of subsequent verification, control and inspection that apply under article 369.

4. The responsible declaration, like the prior notification, does not constitute an administrative authorisation, but solely the transmission of the corresponding information so that the Administration is aware of it and can intervene by means of subsequent control, without prejudice to the powers of inspection.

5. Responsible declarations submitted on the basis of the provisions of future planning instruments shall have no effect.

6. In accordance with the state land law, powers contrary to the legislation or to the applicable territorial or urban planning instrument shall in no case be deemed acquired by responsible declaration or prior notification.

A declaration is not a permit. Under article 289.3 and 289.4, a complete responsible declaration allows the action from the day it is submitted, but it is not an administrative authorisation, and the council keeps its powers of subsequent verification, control and inspection.

Section 2. Planning licences, responsible declarations and prior notifications

Article 290. Types of planning acts subject to administrative intervention.

1. The scope of municipal control shall follow this typology of planning acts subject to administrative intervention:

a) Plotting, segregation or division. Its purpose is to verify that the proposed plotting, segregation, division or alteration of the property complies with territorial and planning legislation and with the applicable planning instruments, without prejudice to any authorisations required under sectoral legislation. Any division or alteration of the surface area of a property, including the various forms of horizontal property, shall be subject to first obtaining a plotting or segregation licence, save for the exceptions expressly provided for in the Act and in the Regulation.

b) Building, works and installations. Its purpose is to verify that the planned actions conform to the provisions of legislation and of the territorial and urban planning instruments in force, including verification that the horizontal divisions resulting from the buildings of which they form part conform to the planning.

c) Urbanisation. Its purpose is to verify that the works related to the urbanisation process comply with territorial and planning legislation and with the applicable planning instruments.

d) Occupation and use. Their purpose is to verify that the intended use of a building, or of part of it, conforms to the applicable rules and to the territorial and urban planning.

Where they concern buildings for which a licence for new construction, extension, modification, renovation or rehabilitation works has been granted or, where applicable, a responsible declaration for works has been submitted, their purpose shall also be to verify the planning conformity of the works carried out with the legally required means of administrative intervention.

Occupation (ocupación) shall be required where the intended use is as a dwelling, and use (utilización) in all other cases.

e) Other stable planning actions. Their purpose is to verify that the planned actions conform to the provisions of legislation and of the planning instruments in force. For the purposes of this Regulation, other stable planning actions are those that involve neither urbanisation nor building but are permanent in character, regardless of their duration, such as the cases indicated in paragraphs b), g), h), i) and j) of article 291.

f) Provisional uses and works. Its purpose is to verify that the provisional uses and works are not expressly prohibited by territorial and planning legislation or by sectoral legislation and do not hinder the implementation of the corresponding planning instrument, the action being subject to the regime provided for in the Act and in article 284.

g) Demolition. Its purpose is the carrying out of demolition works on buildings, constructions or installations.

2. In actions subject to responsible declaration, the scope of the self-check carried out by the interested person shall include compliance with the corresponding purpose according to the type of action concerned under the preceding paragraph.

Article 291. Acts subject to planning licence.

Unless they are acts included in article 292, the following acts are subject to a prior planning licence:

a) Plottings, segregations and planning divisions on any class of land, unless contained in approved reparcelling projects, including the various forms of horizontal property contained in its governing rules. However, no licence shall be necessary for the horizontal division of a property where the number and characteristics of the elements capable of independent use are those resulting from the works licence authorising the construction of the buildings that make up the property, the division being deemed implicit in that licence.

b) Earth movements, including cuttings, terracing, excavations and levelling and any others that exceed the ordinary practice of agricultural work, as well as the draining of wetlands, the creation of waste dumps and the deposit of materials foreign to the characteristics of the land or its natural exploitation, except the stockpiling of materials necessary for carrying out works already authorised by another licence or other legally required enabling precondition, without prejudice to the relevant authorisations for the occupation of the public domain and the other means of administrative intervention provided for in the applicable sectoral rules.

c) Road works and works on infrastructure, services and other urbanisation acts that have to be carried out outside duly approved urbanisation projects, save as expressly provided by the Act for acts promoted by Public Administrations.

d) Construction, building and installation works of any kind that are provisional in character, and provisional uses that do not require works to be carried out.

e) New-build construction, building and installation works, works of extension, modification, renovation or any other works on existing ones that are not subject to responsible declaration, demolition works, except in the case of imminent physical ruin, as well as the installation or placing of prefabricated houses, fixed caravans, mobile homes and similar installations, whether provisional or permanent.

f) The occupation and use of existing buildings or installations, as well as the change of their use in whole or in part, located on rural land or on urban land subject to an urban transformation action, in accordance with the Act and the Regulation.

g) The felling of tree stands and shrub vegetation, and of isolated trees, that are protected by the urban planning instruments.

h) The installation of greenhouses on rural land when this involves any kind of load-bearing structure, excluding domestic greenhouses or those of minor importance in terms of their characteristics or the surface affected.

i) The opening of tracks and access routes to plots on rural land, as well as their modification or paving, except those authorised by the body competent for agriculture, forestry or similar matters.

j) Permanent enclosures, walls and fences of estates and plots on rural land.

k) The carrying out of constructions, buildings and installations on rural land linked to agricultural, livestock, forestry, hunting and mining uses, and any other construction act linked to the rational use of natural resources.

l) Actions for the construction or installation of energy infrastructure, services, facilities or equipment, including those linked to generation from renewable energy sources, and their evacuation infrastructure, whether publicly or privately promoted, and the construction of infrastructure works such as: dams, reservoirs, defence and correction works on public watercourses, irrigation infrastructure, private roads, harbours of refuge, coastal protection and defence dykes, accesses to beaches, bays and roadsteads, and, in general, any type of works or uses that affect the configuration of the territory, save as expressly provided by the Act for acts promoted by Public Administrations.

m) Any other works, constructions, buildings, installations, infrastructure and uses of land, including the subsoil and the airspace, unless they are subject to responsible declaration or are acts not subject to licence under the Act and the Regulation.

Article 292. Acts not subject to planning licence.

1. Acts expressly exempted by the Act and by the applicable sectoral legislation do not require a prior planning licence, and in particular those listed below:

a) Acts subject to responsible declaration or prior notification under the Act and the Regulation.

b) Acts and works promoted by Public Administrations in the cases excepted in the Act and in the Regulation.

c) Acts covered by enforcement orders issued by the town council.

d) Acts necessary to implement administrative or judicial decisions aimed at restoring territorial and planning legality, without prejudice to the submission of a technical project signed by a competent professional in accordance with sectoral rules.

e) Plottings, segregations and planning divisions contained in reparcelling projects.

f) The creation and modification of real estate complexes in the cases excepted in state legislation.

g) Urbanisation acts included in duly approved urbanisation projects. Nor shall a licence be required for urbanisation acts complementary to building actions that are contained in the projects defining those actions.

h) Uses to be carried out on rural land that are needed for agricultural, livestock, forestry, hunting or mining use and exploitation and any other use linked to the rational use of natural resources, where they neither transform the rural nature of the land nor involve the carrying out of works, constructions, buildings and installations, and in particular the following non-construction acts:

1st Earth movements typical of the ordinary practice of agricultural work, such as cultivation, subsoiling, deep ploughing and the forming of ridges.

2nd Revegetation, replanting of woody species, forest planting, ecological restoration, clearing and other work to conserve the plant cover.

3rd The installation of greenhouses, provided that they do not fall among those covered by article 291.1.h).

2. No prior planning licence for segregation is required for the division of the specific lots created on an illegal planning subdivision (parcelación urbanística ilegal) on urban land for which the period laid down in article 153 of the Act has elapsed, not including those for which measures to restore legality are appropriate. In the case of buildings located in subdivisions that are recognised as being in the situation treated as non-conforming (asimilado a fuera de ordenación, AFO), that declaration, which shall cover the building and the specific lot on which it stands, shall have the effects of the planning licence for plotting or segregation, in accordance with article 174.2 of the Act.

Article 293. Acts subject to responsible declaration.

1. The following actions are subject to responsible declaration, without prejudice to the other authorisations or reports required under the Act or the applicable sectoral legislation:

a) Works of minor constructional scope and technical simplicity that do not require a project under the legislation in force.

Municipal by-laws may exempt from responsible declaration those actions which, owing to their technical simplicity and minor constructional and economic scope, such as small installations and works of simple repair, decoration and ornamentation, have no effect on urban planning or on building rules, without prejudice to the cases in which, under the applicable sectoral legislation, such works must be subject to some regime of administrative intervention.

b) Works on existing buildings or installations that conform to territorial and urban planning or are in the legal non-conforming situation (situación legal de fuera de ordenación), located on urban land not subject to urban transformation actions, provided that they do not alter the site coverage and height parameters or entail increases in buildability or in the number of dwellings.

c) Works on existing buildings and installations that conform to territorial and urban planning or are in the legal non-conforming situation, located on rural land, and whose purpose is to improve energy efficiency conditions, to integrate renewable energy installations or to reduce their environmental impact, provided that they do not involve new-build works or an increase in the built surface area.

d) The occupation or use of buildings or installations covered by a prior licence or responsible declaration for works, provided that they are completed and conform to that licence or declaration and their intended use complies with the applicable rules.

e) Occupation and use in existing buildings which, without holding an enabling title for that occupation or use, conform to the planning in force or are in the legal non-conforming situation, located on urban land not subject to urban transformation actions, provided that they have not been the subject of subsequent works carried out without a licence or enabling precondition.

Where works have been carried out without the mandatory means of administrative intervention, they must first be legalised. The decision granting legalisation shall determine the occupation or use of the building, provided that the application for legalisation was accompanied by the documentation required by the Regulation for the occupation or use of existing buildings in which no renovation or adaptation works of any kind need to be carried out.

However, where the works carried out without the enabling precondition are of the kind subject to responsible declaration, both responsible declarations, for the works and for occupation or use, may be submitted together.

f) Changes of use in buildings, or parts of them, that conform to territorial and urban planning or are in the legal non-conforming situation, located on urban land not subject to urban transformation actions, provided that they do not increase the number of dwellings and the use to be established is among those permitted by that planning.

This responsible declaration shall not be required for actions relating to economic activities whose specific legislation, whether state or regional, exempts them from the planning licence procedure and requires a responsible declaration or prior notification to be submitted before they start operating, the planning declaration being deemed implicit in that one.

g) Works on existing buildings and installations on urban land intended for the installation of thermal use of renewable energies in dwellings, the installation of electricity self-consumption with renewable energies of up to 100 kW, and the installation of electric vehicle charging points, except in buildings of the historic and artistic heritage in the category of asset of cultural interest (bien de interés cultural).

h) Alterations in the physical execution of works for which a planning licence has previously been granted, provided that those modifications are not subject to planning licence.

i) Work prior to construction, such as boreholes, surveys, test pits, tests and the clearing of building sites.

j) Research work related to mining activities that does not affect the configuration of the land or involve earth movements subject to planning licence.

k) The installation or placing of prefabricated constructions and similar installations on urban land, where they are shown to be provisional and temporary in character and, in order to start operating, require only works of minor constructional scope and technical simplicity that do not need a project under the legislation in force.

2. The responsible declaration shall be accompanied by the technical project required under the legislation in force, endorsed (visado) where state rules so require, and, where no such project is required, by a descriptive and graphic report defining the general characteristics of its subject matter and of the property on which it is intended to be carried out, where the declaration allows works to be carried out.

3. Responsible declarations for the occupation or use of buildings covered by a works licence or legally required enabling precondition that required a technical project must be accompanied by a certificate evidencing the actual and complete completion of the works, signed by a competent technician and endorsed by the professional association where state rules so require, and evidencing the conformity of the works carried out with the project covering them and, where applicable, with the modifications authorised or declared. The georeferenced graphic representation and the documentation evidencing the commissioning of the installations carried out in the property in accordance with their governing rules shall also be attached and, where applicable, a certificate issued by the utility companies supplying the public services of the correct execution of the connections to the supply networks.

Responsible declarations for occupation or use relating to existing buildings in which no renovation or adaptation works of any kind need to be carried out must be accompanied by a descriptive and graphic certificate, signed by a competent technician and endorsed by the relevant professional association where state rules so require, stating that the work was completed on a specific date, describing the state of repair of the building and the installations it has and evidencing, in view of those circumstances, its suitability for the intended use; together with the cadastral and land registry identification of the property, the georeferenced graphic representation and the planning conditions in force. Documentation evidencing the correct functioning of the installations in the property in accordance with their governing rules shall also be attached and, where applicable, a certificate issued by the utility companies supplying the public services stating that the networks are accessible from the building without new works being needed, and that the connection is feasible.

4. Where actions subject to responsible declaration require a prior administrative authorisation or report for the exercise of the right under the applicable sectoral rules, the submission of the responsible declaration requires those reports or authorisations to have been obtained and to be held beforehand or, where applicable, proof of the silence that has occurred by any means of evidence admitted in law, including the administrative certificate of the administrative silence that has occurred.

5. Town councils, in the exercise of their powers, may by municipal by-law specify any other documentation that must accompany responsible declarations, and may approve standard forms to make it easier for interested persons to provide the data and documentation required. Efforts shall also be made to make these available by electronic means.

6. Actions subject to responsible declaration that are carried out without one having been submitted, where it is mandatory, or that exceed what was declared, shall be considered actions without a licence for all purposes, and the regime for restoring legality and the penalty regime provided for by the Act and the Regulation for acts and uses without a licence shall apply to them.

Works without a declaration. Under article 293.6, actions that needed a responsible declaration and went ahead without one, or went beyond what was declared, are treated as actions without a licence for all purposes, with the restoration of legality and penalty rules that apply to them.

Article 294. Acts subject to prior notification.

Any identification data that must be brought to the attention of the municipality for the exercise of a right are subject to prior notification to the municipality, for the purposes of their record, performance and possible subsequent control, and in particular the following:

a) Changes of holder and the transfer of any planning licences and responsible declarations.

b) The start of works authorised by planning licence where the action concerned requires a technical project under the legislation in force. It shall not be necessary to notify that start in actions subject to responsible declaration.

c) Extensions of the period for starting and completing works with a licence or responsible declaration in force.

d) Withdrawal (desistimiento) from the planning licence or from the responsible declaration submitted.

e) Acts merging estates, plots or building sites that conform to territorial or urban planning.

f) Other data or situations laid down by municipal by-laws, such as the voluntary halting of the actions or a change of the site management team (dirección facultativa).

Article 295. Responsible declarations and licences by phases and partial ones.

1. The town council may grant partial works licences authorising specific phases of a basic building project to be carried out. This shall require the submission of the works execution project for the phase concerned.

The application for a works licence for the execution of the remaining phases must be accompanied, together with the execution project, by a responsible declaration issued by the person who drafted it on its full consistency with the basic building project covered by the previous licence. Otherwise, the modified basic project document must be submitted.

2. As regards actions whose total occupation or use is subject to responsible declaration under the Act and the Regulation, responsible declarations of occupation and use limited to parts of the buildings executed under a prior planning licence or responsible declaration may be submitted, provided that the following requirements are met:

a) That the parts whose occupation or use is sought are technically and functionally capable of being used independently without detriment to the remaining unfinished parts.

b) That, in the execution of the rest of the works previously authorised or declared, the time limits and other provisions imposed by the applicable rules are being complied with at the time of submission.

c) That the partial occupation or use does not seriously interfere with the completion of the works.

d) That the part whose occupation or use is sought was executed entirely in accordance with the project covering it and, where applicable, with the modifications submitted and the conditions laid down.

In the case of occupation or use not subject to responsible declaration, occupation or use licences limited to parts of the constructions and installations may be granted, provided that the above requirements are met.

3. Occupation or use licences limited to parts of constructions and installations that comply with planning rules may also be granted where there are other parts that do not comply with those rules in matters of detail or of minor importance, provided that paragraph 2, letters a), b) and c), is complied with, without prejudice to the exercise of any planning discipline powers that apply. In this case, a responsible declaration shall not be submitted.

Article 296. Acts promoted by Public Administrations.

For planning acts promoted by a Public Administration or by entities attached to or dependent on it, article 139 of the Act shall apply.

Where this sits

Next: Licence procedure, validity and transfer. Related: the LISTA Act on licences and irregular buildings. All translated laws: Spanish laws in English.

Related on voixa.es: Personal tax in Andalusia; Spain’s 100% property tax for non-EU buyers: what happened.

Nothing here is advice on your own position, and this reading is not the official text. Spain publishes no official English version of this decree; where the wording matters to a decision, read it against the Spanish original published in the BOJA.