The General Regulation of the Andalusian Land Sustainability Act (Decree 550/2022), articles 297 to 311: who grants planning licences, the application and its documents, project endorsement, the technical and legal reports, the content of the decision, the three-month time limit and administrative silence. Also the nullity of licences, licences overtaken by new planning, the validity periods and lapse of licences and responsible declarations, their transfer, starting works on an execution project and changes during works.

Unofficial English translation from the Spanish by Voixa Consultors S.L. Alexander Baranov is responsible for the translation. Source: Decreto 550/2022, de 29 de noviembre, por el que se aprueba el Reglamento General de la Ley 7/2021, de 1 de diciembre, de impulso para la sostenibilidad del territorio de Andalucía, text as published in BOJA no. 232 of 2 December 2022, BOJA ↗. This is the original text, not a consolidated one: later amendments (including those made by Law 5/2025, the Andalusian Housing Act, to articles 83 and 195.4, which are not on these pages) and the correction of errors published in BOJA no. 241 of 2022 are not reflected. Check wording, figures, dates and legal effect against the Spanish original before relying on this reading. Source snapshot: 10 November 2026. This page: Title VI, Chapter II, Sections 3 and 4, articles 297 to 311. Three pages translate articles 287 to 314 on licences and other means of administrative control, and chapter I of Title VIII on irregular buildings in the AFO situation; the rest of the Regulation is not translated.

Title VI. Building activity (continued)

Chapter II. Means of administrative intervention on building activity (continued)

Section 3. Procedure for granting planning licences

Article 297. Competence to grant planning licences.

The competence to grant planning licences lies with the municipal body determined by the legislation and rules applicable to local government.

Article 298. General rules on the procedure.

1. The procedure for granting planning licences must be processed and decided in accordance with the legislation on local government and on the common administrative procedure, with the procedural specialities established in the territorial and planning legislation of the Autonomous Community of Andalusia and with the particular rules established in the following paragraphs.

2. Municipalities may regulate, by means of the corresponding Ordinances, the procedure for granting planning licences, in keeping with the rules referred to in paragraph 1.

3. The procedure for granting planning licences must necessarily include a technical report and a legal report from the corresponding municipal services or, failing them, from the Provincial Council (Diputación Provincial) in accordance with the local government rules and in the form and cases determined by the corresponding provincial rules, on whether the intended act conforms to the provisions of the applicable legislation and territorial and urban planning; the holder of the Secretariat of the Town Council, or the competent body in large municipalities, must give warning of the omission of either of them on the terms provided in the local government rules.

4. In the procedure for granting planning licences, all the formalities and actions established by sectoral rules by reason of the specific content of the planning action concerned shall be complied with, on the terms and with the effects on the procedure provided in those rules.

5. Simultaneous applications for licences which, relating to the same property or part of it, concern acts subject to planning licence in accordance with article 291 shall be processed jointly in a single procedure. The decision adopted shall distinguish each of the licences granted, each retaining its own nature.

Article 299. Initiation of the procedure.

1. The procedure for granting planning licences shall be initiated by filing an application addressed to the Town Council accompanied by documentation enabling its subject matter to be sufficiently understood. In particular:

a) The application shall sufficiently define the acts of construction or building, installation and use of the land, airspace and subsoil that are intended to be carried out, identifying in it both the developer (promotor) and the technical professionals involved in the project and, where applicable, the works management (dirección facultativa) and the health and safety coordinator. For these purposes applications must attach a technical project, signed by a competent professional, with the level of detail established by sectoral legislation, defining the number and characteristics of the elements capable of independent use where it contains horizontal property arrangements.

For the grant of licences for the execution of building works, submission of a basic project shall be sufficient, but execution of the works may not begin without prior submission of an execution project duly endorsed (visado) by the relevant professional association where State rules so require.

Where a technical project is not required, applications shall be accompanied by a descriptive and graphic report defining the general characteristics of their subject matter and of the property on which it is intended to be carried out.

b) Applications concerning new constructions or installations, and extensions of them, must state their intended use, which must be consistent with the characteristics of the construction or installation.

c) An application for a licence for subdivision, segregation or division must attach a subdivision project signed by a competent technical professional, which shall include georeferenced plans at an appropriate scale of the location and area of the land affected by the alteration and of the initial and resulting properties and plots, as well as their cadastral and land registry identification and the planning conditions in force.

d) For actions subject to an occupation or use licence, the application shall be accompanied by the documentation detailed in article 293.3, according to the specific content of the planning action concerned.

e) For actions on rural land, the application must sufficiently identify the property that is the subject of the acts subject to licence, by its cadastral reference and, where applicable, its land registry property number. This is without prejudice to the prior authorisation provided for in the Act for extraordinary actions on rural land, which qualifies the land where they are intended to be located; the licence must be applied for within a maximum of one year from that authorisation.

f) Every licence application must include a georeferenced graphic representation of the action concerned, stating, where applicable, the UTM coordinates of the area to be occupied by the buildings, for works licences, or of the perimeter of each of the resulting properties, in the case of subdivision or segregation. In the case of buildings under the horizontal property regime, georeferencing shall be required only for the portion of land occupied by the building as a whole, while the location and boundaries of each independent element shall be specified by its respective graphic representation.

2. The application shall also be accompanied by the documentation, authorisations and reports that sectoral legislation or the applicable territorial and planning rules require before the grant of a licence and, where applicable, the authorisation or concession for occupation or use of the public domain. Town Councils may not grant a licence without prior submission of the mandatory sectoral authorisations, concessions and reports that other Public Administrations must grant. Licences may not be granted conditional on their being obtained in the future.

3. Town Councils, in the exercise of their powers, may determine by Municipal Ordinance any other documentation that must accompany licence applications, and may approve standard planning licence application forms to make it easier for interested parties to provide the data and documentation required. Efforts shall also be made to make them available by electronic means.

4. Town Councils shall determine by Municipal Ordinance the actions that, by their nature or lesser technical scale, do not require technical projects to be submitted, and the documents required in each case according to the type of action concerned.

Article 300. Endorsement.

1. As a general rule, projects may be submitted voluntarily to the corresponding Professional Association for endorsement (visado). However, endorsement shall be mandatory in the cases established in State rules.

2. For works promoted by Public Administrations or their attached entities, and by bodies dependent on them, provided the projects are drawn up within the framework of an official, employment or contractual relationship between the Administration and the competent professional, endorsement may be replaced by the intervention of the project supervision office or equivalent body, or by the check carried out in the public procurement process, where applicable.

3. The endorsement granted by the corresponding Professional Association shall clearly state its subject and shall evidence to the municipal Administration at least the following circumstances:

a) The identity and professional qualification of the technical professional who authored the work.

b) The formal correctness and completeness of the documentation of the professional work in accordance with the rules applicable to the work concerned.

Article 301. Remedying and repeating applications.

1. If the application does not meet the requirements, the applicant shall be required to remedy the defect or attach the mandatory documents within a period of not less than ten days nor more than twenty, depending on the complexity of the deficiencies or of the documents to be provided, with notice that if they fail to do so they shall be deemed to have withdrawn their application, following a decision so declaring.

2. Once withdrawal of the licence application referred to in paragraph 1 has been declared, or where the lapse of the procedure has been declared, a new licence may be applied for by providing the documentation or by requesting that the documentation contained in the archived file be incorporated into the new file.

Article 302. Technical and legal reports.

1. The municipal technical and legal services or, failing them, the corresponding services of the Provincial Council in accordance with the local government rules and in the form and cases regulated by the corresponding provincial rules, must issue the corresponding technical and legal reports before the proposed decision, ruling on whether the licence application conforms to the territorial and planning rules on the terms set out in article 288.

The technical report must verify that the action conforms to the applicable territorial and urban planning and verify that all the required documentation has been submitted, in accordance with the territorial and planning rules and the applicable sectoral legislation.

The legal report shall contain a statement of facts, the list of applicable legal provisions and a legal analysis of whether the intended action is lawful and of whether the procedure is appropriate.

2. If the content of those reports reveals deficiencies that can be remedied, before the proposed decision is drafted the applicant shall be required, once only, stating the deficiencies detected and the provisions of the territorial and planning rules infringed, to remedy them within a period not exceeding one month.

3. If the deficiencies have not been remedied within the periods indicated, the interested party shall be deemed to have withdrawn the application, following a decision that must be issued on the terms provided in the rules governing the common administrative procedure.

4. In the light of the reports issued, the proposed decision shall contain an analysis of whether the intended action is lawful and of whether the procedure followed conforms to the applicable rules.

5. The technical and legal reports and the proposed decision must conclude with a clear and precise statement enabling the competent municipal body to adopt a decision in accordance with the legal order.

Article 303. Decision.

1. Decisions granting or refusing planning licences must state reasons and be consistent with what was applied for.

2. Payment of fees or taxes, or municipal tolerance, shall not imply the grant of a licence; actions carried out without a licence are regarded as clandestine and unlawful and are not legitimised by the passage of time, and the municipal authority may order the action to be halted or to cease.

3. The decision granting the licence must expressly record, in addition to any other specifications required by the provisions in force or which the competent body considers appropriate to include, the following particulars:

a) Planning classification and zoning (clasificación y calificación urbanística) of the land that is the subject of the action.

b) Purpose of the action and the use to which it will be put.

c) Material execution budget.

d) Situation and location of the works, with their cadastral identification and, where applicable, the georeferencing of the land occupied by the action concerned, stating, where appropriate, the land registry property number in the case of urban subdivisions and actions on rural land. Licences for subdivision, segregation or division shall reflect the georeferencing of the initial and resulting properties and plots affected by the alteration, and for this purpose a certified copy of the georeferenced plans submitted may be incorporated into the municipal decision granting the planning licence.

e) Name or business name of the developer.

f) Technical professional who authored the project and, where applicable, the works management.

g) Periods for starting and completing the works, and possibility of extension.

4. The technical documentation or technical project, once the corresponding licence has been granted, shall be incorporated into it as a material condition of the licence.

Article 304. Period for decision.

1. The express decision must be notified within a maximum period of three months. The maximum period within which the decision must be notified shall begin to run from the date on which the complete documentation is filed in the electronic register of the Town Council competent to decide, and may be suspended in the cases provided in the legislation on the common administrative procedure, including the following:

a) Periods for remedying deficiencies in the application.

b) Mandatory public information periods established by legislation, and suspension of the grant of licences.

c) Periods for granting authorisations or issuing mandatory reports under the territorial and planning rules or sectoral legislation.

2. Once the period established in paragraph 1 has passed without the express decision on the planning licence having been notified, the licence may be understood to have been granted, except in those cases where an express act of conformity, approval or administrative authorisation is required, in accordance with the State land legislation.

Accordingly, acts authorising the following shall be express, with negative administrative silence where the maximum period expires without an express decision having been notified:

a) Earth movements and levelling that are independent of urbanisation, building or construction projects on rural land.

b) New building works on any class of land, and the construction and installation of new installations on rural land.

c) The placing of prefabricated houses and similar installations, whether provisional or permanent, on rural land.

d) The felling of tree masses or shrub vegetation arising from the legislation on protection of the public domain.

3. In no case may powers or rights contrary to the applicable legislation or territorial or urban planning be understood to have been acquired by administrative silence.

4. Works licences and occupation or use licences granted by positive administrative silence may be evidenced by any means of proof admitted in law, including the certificate evidencing the silence that has occurred, in accordance with the rules on the common administrative procedure.

The certificate shall be issued ex officio, within fifteen days from the expiry of the maximum period for deciding the procedure, by the body which, under the local government rules, holds the function of certifying the administrative acts issued by the body competent to grant licences. In any event, the interested party may request it at any time, and it must be issued within the non-extendable period of fifteen days from the day following that on which the request was entered in the electronic register of the Administration or Body competent to decide.

If the Town Council does not issue the certificate of the presumed act in the case of licences for new buildings under construction and occupation or use licences, where the action concerned is subject to this means of intervention, a public deed may be executed if the interested person proves to the notary that the application for the corresponding licence has been filed with the municipality, that the certificate of the presumed act has been requested, and expressly states that no reply has been received within the legally established periods.

Silence under article 304. A licence not decided and notified within three months of the complete file may be understood as granted, but new building works on any class of land, new installations and prefabricated houses on rural land, and the other acts listed in paragraph 2 need an express decision: there, silence means refusal.

Section 4. Legal regime of the means of administrative intervention

Article 305. Grounds for nullity of administrative titles.

Without prejudice to the grounds for nullity provided in the legislation in force, licences and administrative acts granted contrary to the provisions of territorial and urban planning shall be null and void, in accordance with article 137.3 of the Act, where they concern the carrying out of the acts and uses referred to in article 153.2 of the Act.

Article 306. Means of intervention not in conformity with new urban planning.

1. Where planning licences or responsible declarations subsequently cease to conform to the new applicable territorial or urban planning, by virtue of the approval of a new prevailing planning instrument or of an amendment (innovación) of the instrument in force at the time of their grant or of the filing of the enabling instrument, and the acts have not yet been completed, the municipality, where starting or completing them could appreciably hinder the new planning, may declare, with reasons and after hearing the interested parties, their non-conformity with the territorial or urban planning.

2. This declaration of non-conformity shall entail the immediate suspension of the effectiveness of the licence or the responsible declaration where the acts have not started, and the immediate halting of the building acts covered by them where they have started. In both cases for a maximum period of four months. Within the period during which the suspension is in force and after hearing the interested parties, the revocation of the licence or, where applicable, the termination of the effects of the responsible declaration may be declared, in whole or in part, determining the terms and conditions on which the acts may be started or continued and completed. Any compensation due shall be fixed, where applicable.

Article 307. Time validity and lapse of licences.

1. Planning licences shall be granted for a specified period both for starting and for completing the acts covered by them, except for actions which, by their nature, have indefinite validity. If the period is not expressly determined, they shall be understood to be granted under the legal condition of observing one year to start the works and three years to complete them.

2. Those periods may be extended before they expire by filing a prior notification, justifying the grounds and the new period, which may not exceed that initially agreed. The extension to start the works may not be exercised where there are changes to the urban planning in force at the time the licence was granted. For the extension to complete works already started, the planning in force at the time the licence was granted shall apply.

The licence’s period of effectiveness shall be suspended if it cannot be executed for reasons attributable to the Administration.

Obtaining an extension of the period to start the works does not, in itself, entail an extension of the period to complete them.

3. The periods for starting and completing the works shall be counted from the day following that of notification to the applicant of the grant of the licence or, failing that, from the day following that of the expiry of the maximum period for deciding and notifying.

4. Licences shall lapse in the following cases:

a) Where execution of the actions covered by them has not started within the period indicated or, failing that, within one year, save for reasons not attributable to the licence holder.

b) Where the work is not completed within the period indicated or, failing that, within three years, save for reasons not attributable to the licence holder.

c) Municipal licences for subdivisions, segregations or divisions are granted and issued on condition that the public deed containing the act of subdivision is filed with the municipality within the three months following their grant or issue. Failure to file the public deed in time determines the lapse of the licence by operation of law, without the need for any implementing act. The filing period may be extended for justified reasons. In the same deed containing the act of subdivision and the relevant attested licence, the parties executing it must require the authorising notary to send an authorised copy of it to the corresponding Town Council through the regulatory channel.

5. The body competent to grant the licence shall declare, ex officio or at the request of any person, its lapse, once any of the periods referred to in paragraphs 1 and 2 of this article have passed and not been met, save for reasons not attributable to the licence holder. Once the procedure aimed at declaring the lapse has begun, the halting of the acts covered by the licence may be ordered as a provisional measure. The declaration of lapse must be issued after hearing the interested parties for a period of fifteen days, and must be notified within three months from the start of the procedure. If notification is not made within that period, the provisional measure halting the works, if one was adopted, shall cease to have effect and the lapse procedure must be archived.

6. The declaration of lapse shall extinguish the effects of the licence. Once the declaration of lapse has been notified, a new planning licence must be applied for and obtained in order to start or complete the land use acts for which it was granted. Until it is granted, no works may be carried out other than those strictly necessary to guarantee the safety of persons and property and the value of what has already been done, subject to prior authorisation or order of the Town Council. With these exceptions, planning actions carried out after the lapse of the licence has been declared shall be regarded as unauthorised and shall give rise to the adoption of the necessary territorial or urban planning enforcement (disciplina) measures.

7. Once two months have passed from notification of the declaration of lapse without a new licence having been applied for or, where applicable, once the licence applied for has been refused, the corresponding plot or building plot shall be declared to be in the situation of execution by substitution, on the terms provided in the Act, or, where applicable, the corresponding territorial or urban planning enforcement procedure shall be initiated.

Default periods under article 307. Where the licence sets no periods, the works must start within one year and be completed within three; a subdivision, segregation or division licence lapses automatically if the public deed is not filed with the municipality within three months.

Article 308. Time validity and lapse of responsible declarations.

1. The responsible declaration authorises the acts covered by it to be carried out for a period that may not exceed six months to start the actions and two years to complete them, except for actions relating to occupations or uses and changes of use which, by their nature, have indefinite validity.

2. The periods for starting and completing the works shall be counted from the date the responsible declaration is filed with the corresponding Town Council; before the end of the periods determined, a notification of extension may be filed for justified reasons and for a new period not exceeding half of that initially established, provided that the action covered by the responsible declaration conforms to the territorial or urban planning in force at the time the extension is requested.

The responsible declaration’s period of effectiveness shall be suspended if it cannot be executed for reasons attributable to the Administration.

3. Once the periods indicated in this article have passed and not been met, the competent body shall declare, after hearing the interested party for a period of ten days, the lapse of its effects, requiring a new responsible declaration to be filed, without prejudice, where applicable, to the initiation of the corresponding planning enforcement procedure.

Article 309. Transfer of the means of administrative intervention.

1. Planning licences and responsible declarations shall be transferable, and the acquirer and the transferor must notify the Town Council, failing which both shall be jointly and severally subject to the liabilities arising from the action. The notification shall state the licence or responsible declaration intended to be transferred. The notification by the previous holder may be replaced by the public or private document evidencing the inter vivos or mortis causa transfer of them, or of the ownership or possession of the property, provided that such transfer includes that of the licence or the responsible declaration.

Where the subject of the means of administrative intervention is the execution of works, the acquirer must undertake, in the notification addressed to the Town Council, to execute the works in accordance with the content of the planning licence granted or of the responsible declaration and, where applicable, with the technical project submitted that supports it.

2. The transfer of means of administrative intervention relating to actions of use or management of public domain property shall be governed both by the applicable public property legislation and by the conditions that have been established.

Article 310. Execution of building works.

1. Where licences for building works have been granted solely on submission of the basic Project, the building works may not start until the notification of start of works has been filed with the Town Council, accompanied by the execution Project duly endorsed, where State rules so require, or supervised by the project supervision office or equivalent body or, where applicable, approved in the public procurement process.

The said Project shall be accompanied by a responsible declaration by a competent technical professional on the consistency between the basic project and the execution project, by the partial projects or other technical documents on specific technologies or installations of the building which complement or develop it, and by such other documentation provided for by sectoral rules as must be submitted to the Town Council for the execution of works.

Submission of the documentation referred to in this paragraph shall enable the works covered by the licence to start.

2. If the execution project submitted incorporates modifications to the basic project corresponding to actions subject to responsible declaration under the Act and the Regulation, filing the responsible declaration, together with the execution Project and in accordance with the requirements established in this Regulation, shall enable the works covered by the licence to start, in accordance with the modifications declared.

In the above case, the technical declaration of consistency shall describe those modifications and justify why they are not subject to licence.

3. If the execution project drawn up incorporates modifications to the basic project whose execution could not be carried out by means of a responsible declaration, a new licence must be obtained for the execution of the works.

4. Filing the prior notification of start of works shall in no case cover modifications to the basic project that have not been expressly declared and shall not prevent the adoption, where applicable, of the appropriate measures to restore territorial or urban planning legality.

Filing the prior notification of start of works shall not imply the Administration’s agreement with the technical solutions adopted in the execution project as regards compliance with the basic requirements of building, nor shall it alter the regime of liability established in the rules governing building.

Article 311. Modifications during the execution of works.

1. If, during the material execution of works covered by a planning licence, alterations to them become necessary, a planning licence must be obtained whose subject shall be the alteration concerned. If those alterations correspond to actions subject to responsible declaration, under the Act and the Regulation, they shall be subject to that means of administrative intervention, without the need to apply for and obtain a new licence.

2. Where alterations become necessary in the material execution of works covered by a responsible declaration that has been filed, those alterations must be the subject of a responsible declaration before they are executed, in accordance with the requirements established in this Regulation.

If the necessary alterations go beyond the cases subject to responsible declaration, a works licence must be granted before they are executed. In this case, the planning licence application shall define the acts of construction, installation and use intended to be carried out and shall incorporate the actions previously declared.

Where this sits

Previous: Licences, responsible declarations and notifications. Next: Utilities, the Land Registry and AFO buildings. The Act these articles implement: Andalusian planning law: licences, illegal builds and AFO status. All translated laws: Spanish laws in English.

Related on voixa.es: Personal tax in Andalusia; Spain’s 100% property tax for non-EU buyers: what happened.

Nothing here is advice on your own position, and this reading is not the official text. Spain publishes no official English version of this decree; where the wording matters to a decision, read it against the Spanish original published in the BOJA.