Liability for defects, insurance and money paid off-plan

Law 38/1999, articles 17 to 20 and the additional, transitional and final provisions: the ten-, three- and one-year liability of each agent for defects in a building, the two-year limitation period, the compulsory ten-year insurance without which a new building cannot be deeded or registered, and the bank guarantee or insurance that must secure every euro a buyer pays a developer before completion.

Unofficial English translation from the Spanish by Voixa Consultors S.L. Alexander Baranov is responsible for the translation. Source: Ley 38/1999, de 5 de noviembre, de Ordenación de la Edificación, consolidated text, last modified 15 June 2022, BOE-A-1999-21567 ↗. Check wording, figures, dates and legal effect against the Spanish original before relying on this reading. Source snapshot: 5 November 2026. The fifth additional provision, which rewrites articles 54 and 55 of the Compulsory Expropriation Act of 1954, is summarised and its text not reproduced; everything else is translated.

The two protections a buyer of a new home has

Before completion, the money. Under the first additional provision a developer may take advance payments for a home only into a special bank account and only if each payment, with taxes and legal interest, is secured by an individual insurance policy or a bank guarantee issued in the buyer’s name. If the building is not started or not delivered on time, the buyer can demand the money back from the developer and, thirty days later, from the insurer or bank.

After completion, the building. Under article 17 every agent who took part answers to the owners, and to later buyers, for structural defects for ten years and for defects affecting habitability for three, and the builder for finishing defects for one. For homes the ten-year cover must be insured: under article 20 the notary cannot authorise, and the Land Registry cannot register, the declaration of a new building without proof of that insurance.

Chapter IV. Liability and guarantees

Article 17. Civil liability of the agents taking part in the building process

1. Without prejudice to their contractual liabilities, the natural or legal persons taking part in the building process shall be liable to the owners and to subsequent purchasers of the buildings, or of parts of them where they are divided, for the following material damage caused in the building within the periods indicated, counted from the date of handover of the works without reservations or from the remedying of the reservations:

a) For ten years, for material damage caused in the building by flaws or defects affecting the foundations, supports, beams, floor slabs, load-bearing walls or other structural elements and directly compromising the mechanical strength and stability of the building.

b) For three years, for material damage caused in the building by flaws or defects in the constructive elements or installations that result in failure to meet the habitability requirements of article 3.1.c).

The builder shall also be liable for material damage due to flaws or defects of execution affecting finishing elements of the works within a period of one year.

2. Civil liability shall be enforceable personally and individually, both for one’s own acts or omissions and for the acts or omissions of persons for whom, under this Act, one must answer.

3. However, where the cause of the material damage cannot be attributed to an individual agent, or concurrent fault is duly proven without the degree of each agent’s involvement in the damage being determinable, liability shall be joint and several. In any event, the developer shall be jointly and severally liable with the other agents involved to purchasers for material damage in the building caused by flaws or defects of construction.

4. Without prejudice to any administrative measures that may apply in each case, the developer’s liability established in this Act shall extend to the natural or legal persons who, under the contract or by reason of their decisive involvement in the development, act as developers in the form of a developer or manager of cooperatives or of communities of owners or other similar arrangements.

5. Where the project has been commissioned jointly from more than one designer, they shall be jointly and severally liable.

Designers who commission calculations, studies, opinions or reports from other professionals shall be directly liable for damage arising from their insufficiency, incorrectness or inaccuracy, without prejudice to any recourse they may have against their authors.

6. The builder shall be directly liable for material damage caused in the building by flaws or defects arising from lack of skill, lack of professional or technical capacity, negligence or failure to perform the obligations of the site foreman and the other natural or legal persons dependent on the builder.

Where the builder subcontracts the execution of certain parts or installations of the works to other natural or legal persons, it shall be directly liable for material damage due to flaws or defects in their execution, without prejudice to any recourse that may lie.

The builder shall likewise be directly liable for material damage caused in the building by deficiencies in construction products acquired or accepted by it, without prejudice to any recourse that may lie.

7. The site manager and the construction manager who sign the final certificate of works shall be responsible for the truthfulness and accuracy of that document.

Whoever accepts the management of works whose project they did not prepare themselves shall assume the liabilities arising from omissions, deficiencies or imperfections in the project, without prejudice to any recourse they may have against the designer.

Where site management is commissioned jointly from more than one technician, they shall be jointly and severally liable, without prejudice to the apportionment between them.

8. Liability for damage shall not be enforceable against the agents taking part in the building process if it is proven that the damage was caused by fortuitous event, force majeure, the act of a third party or the injured party itself.

9. The liabilities referred to in this article are without prejudice to those borne by the seller of the buildings or built parts towards the buyer under the contract of sale between them, articles 1484 et seq. of the Civil Code and the other legislation applicable to sale.

Sue the developer, whoever was at fault. Paragraph 3 makes the developer jointly liable with every other agent towards purchasers. A buyer does not have to prove whether the architect or the builder caused the crack: the developer answers for both, and settles with them afterwards. Paragraph 9 keeps the seller’s separate liability under the Civil Code and the sale contract alongside this one.

Article 18. Limitation periods for actions

1. Actions to enforce the liability provided for in the preceding article for material damage arising from flaws or defects shall become time-barred two years after the damage occurs, without prejudice to any actions that may remain to enforce liability for breach of contract.

2. Any recourse action that one agent taking part in the building process may have against the others, or that insurers may have against them, shall become time-barred two years after the judgment ordering the liable party to pay compensation for the damage becomes final, or from the date on which compensation was paid out of court.

Two clocks, not one. The damage must appear within the ten, three or one years of article 17, and the claim must then be brought within two years of the damage appearing. A crack that shows in year nine can still be claimed in year eleven; one noticed in year nine and left until year twelve cannot.

Article 19. Guarantees for material damage caused by flaws and defects of construction

1. The guarantees required for the building works covered by article 2 of this Act shall take effect in accordance with the compulsory nature established under the second additional provision, taking the following guarantees as the reference:

a) Material damage insurance, surety insurance or a financial guarantee, to secure for one year compensation for material damage due to flaws or defects of execution affecting finishing elements of the works, which may be replaced by the developer’s retention of 5 per cent of the amount of the material execution of the works.

b) Material damage insurance, surety insurance or a financial guarantee, to secure for three years compensation for damage caused by flaws or defects in the constructive elements or installations resulting in failure to meet the habitability requirements of article 3.1.c).

c) Material damage insurance, surety insurance or a financial guarantee, to secure for ten years compensation for material damage caused in the building by flaws or defects originating in or affecting the foundations, supports, beams, floor slabs, load-bearing walls or other structural elements and directly compromising the mechanical strength and stability of the building.

2. Material damage insurance shall meet the following conditions:

a) The policyholder shall be the builder in case a) of paragraph 1 and the developer in cases b) and c) of that paragraph, and the insured shall be the developer itself and the successive purchasers of the building or of part of it. The developer may expressly agree with the builder that the builder shall be the policyholder on the developer’s behalf.

b) The premium must be paid at the time of handover of the works. However, where payment in instalments in periods after the date of handover has been agreed, failure to pay subsequent instalments of the premium shall not entitle the insurer to terminate the contract, nor shall the contract be extinguished, the insurer’s cover suspended or the insurer released from its obligation, should the insured need to enforce the guarantee.

c) The rules on cover of extraordinary risks to persons and property in article 4 of Law 21/1990 of 19 December shall not apply.

3. Surety insurance shall meet the following conditions:

a) Those set out in paragraphs 2.a) and 2.b) of this article. As regards paragraph 2.a), the insured shall always be the successive purchasers of the building or of part of it.

b) The insurer undertakes to compensate the insured on first demand.

c) The insurer may not raise against the insured the defences it may have against the policyholder.

4. Once the insurance cover takes effect, the contract may not be rescinded or terminated by mutual agreement before the end of the term provided for in paragraph 1 of this article.

5. The minimum sum insured shall be:

a) 5 per cent of the final cost of the material execution of the works, including professional fees, for the guarantees in paragraph 1.a) of this article.

b) 30 per cent of the final cost of the material execution of the works, including professional fees, for the guarantees in paragraph 1.b) of this article.

c) 100 per cent of the final cost of the material execution of the works, including professional fees, for the guarantees in paragraph 1.c) of this article.

6. The insurer may choose between paying compensation in cash corresponding to the valuation of the damage or repairing it.

7. Failure to comply with the above rules on compulsory guarantees shall in all cases entail the personal liability of the person obliged to take out the guarantees.

8. For the guarantees referred to in paragraph 1.a) of this article, clauses introducing excesses or any limitation of the insurer’s liability to the insured shall not be admissible.

Where an excess is established in the insurance contract referred to in paragraphs 1.b) and 1.c) of this article, it may not exceed 1 per cent of the sum insured for each registered unit.

9. Unless otherwise agreed, the guarantees referred to in this Act shall not cover:

a) Bodily injury or other economic loss other than the material damage guaranteed by the Act.

b) Damage caused to properties contiguous or adjacent to the building.

c) Damage caused to movable property located in the building.

d) Damage caused by alterations or works carried out in the building after handover, except works to remedy the defects observed at handover.

e) Damage caused by misuse or lack of proper maintenance of the building.

f) The costs necessary for maintaining a building already handed over.

g) Damage originating in fire or explosion, except where due to flaws or defects in the building’s own installations.

h) Damage caused by fortuitous event, force majeure, the act of a third party or the injured party itself.

i) Claims originating in parts of the works subject to reservations recorded in the handover record, until those reservations have been remedied and the remedying is recorded in a new record signed by the signatories of the handover record.

Only the ten-year policy is compulsory. Paragraph 1 lists three guarantees, but under the second additional provision only the ten-year structural cover in letter c) is required, and only for buildings whose main use is housing. The one- and three-year guarantees exist only if a royal decree makes them compulsory or the parties agree on them; the liability in article 17 remains either way.

Article 20. Requirements for deeds and registration

1. Public deeds declaring a new building to which this Act applies shall not be authorised or registered in the Land Registry unless the constitution of the guarantees referred to in article 19 is evidenced and attested.

2. Until the limitation periods for the actions referred to in article 18 have expired, the sheet opened for an individual developer in the Commercial Registry shall not be closed, nor shall the liquidation of developer companies be registered, without prior proof to the Registrar that the guarantees established by this Act have been constituted in respect of each and every building they have developed.

Additional provisions

First additional provision. Receipt of amounts on account of the price during construction

One. Obligations of developers receiving advance payments.

1. Natural and legal persons developing the construction of any type of dwelling, including those carried out under the regime of a community of owners or a cooperative, who intend to obtain payments of money from purchasers for their construction, must meet the following conditions:

a) To guarantee, from the grant of the building licence, the return of the amounts paid plus legal interest, by means of a surety insurance contract with insurers duly authorised to operate in Spain, or by a joint and several guarantee issued by duly authorised credit institutions, in the event that construction is not started or not completed within the period agreed for delivery of the dwelling.

b) To receive the amounts advanced by purchasers through credit institutions, where they must be deposited in a special account, separate from any other kind of funds belonging to the developer, including in the case of communities of owners or cooperatives, and which may be drawn on only for purposes arising from the construction of the dwellings. To open these accounts or deposits, the credit institution shall, under its own responsibility, require the guarantee referred to in the preceding condition.

2. The guarantee shall extend to the amounts contributed by purchasers, including applicable taxes, plus the legal interest rate.

Two. Requirements for the guarantees.

1. For a surety insurance contract to serve as a guarantee of the amounts advanced in the construction and sale of dwellings, it must meet the following requirements:

a) An individual insurance policy shall be taken out for each purchaser, identifying the property for whose acquisition the amounts or commercial instruments are paid in advance.

b) The sum insured shall include the total amount of the sums advanced under the contract of sale, the contract of adhesion to the development or phase of the cooperative or equivalent legal instrument, including applicable taxes, increased by the legal interest rate from the effective payment of the advance until the date scheduled for delivery of the dwelling by the developer.

c) The policyholder shall be the developer, who shall pay the premium for the whole insurance period until the contract of sale, of adhesion to the development or phase of the cooperative or equivalent legal instrument is executed as a public deed.

d) The insured shall be the purchaser or purchasers named in the contract of sale.

e) The insurer may not raise against the insured the defences it may have against the policyholder. The developer’s failure to pay the premium shall in no case be a defence that can be raised.

f) The term of the contract may not be shorter than that of the undertaking to build and deliver the dwellings. Where an extension is granted for delivery of the dwellings, the developer may extend the insurance contract by paying the corresponding premium and must inform the insured of the extension.

g) During the term of the insurance the insurer may examine the documents and data of the developer-policyholder relating to the obligations assumed towards the insured.

h) If construction is not started or not completed within the agreed period, the insured, provided that they have reliably demanded that the developer return the amounts contributed on account, including applicable taxes and interest, and the developer has not returned them within thirty days, may claim the corresponding compensation from the insurer. The insured may likewise claim directly from the insurer where it is not possible to claim first from the developer.

The insurer must compensate the insured within thirty days of the claim being made.

i) Amounts not shown to have been contributed by the insured shall in no case be compensated, even if they have been included in the sum insured under the insurance contract, because their payment was deferred under the assignment contract.

j) The insurer may claim from the developer-policyholder the amounts paid to the insured, for which purpose it shall be subrogated to the insured’s rights.

k) Where the insurer has paid compensation to the insured as a result of a loss covered by the insurance contract, the developer may not dispose of the dwelling without first reimbursing the insurer the amount paid.

l) In everything not specifically provided for, Law 50/1980 of 8 October on Insurance Contracts shall apply.

2. For a bank guarantee to serve as a guarantee of the amounts advanced in the construction and sale of dwellings, it must meet the following requirements:

a) It must be issued and kept in force by the credit institution for the total amount of the sums advanced under the contract of sale, the contract of adhesion to the development or phase of the cooperative or equivalent legal instrument, including applicable taxes, increased by the legal interest rate from the effective payment of the advance until the date scheduled for delivery of the dwelling by the developer.

b) If construction is not started or not completed within the agreed period, the beneficiary, provided that they have reliably demanded that the developer return the amounts paid on account, including applicable taxes and interest, and the developer has not returned them within thirty days, may demand payment of those amounts from the guarantor. The beneficiary may likewise claim directly from the guarantor where it is not possible to claim first from the developer.

c) Two years after the developer’s failure to perform the guaranteed obligation, if the purchaser has not demanded rescission of the contract and return of the amounts advanced, the guarantee shall lapse.

A bank guarantee lapses after two years. Under letter 2.c) a buyer protected by a bank guarantee who does nothing for two years after the developer fails to deliver loses it. When a development stalls, send the reliable demand under letter b) well inside those two years, by a means that proves receipt and content, such as a burofax.

Three. Contractual information.

Contracts for the acquisition of dwellings in which the payment of advance amounts to the developer is agreed, including in the case of communities of owners or cooperatives, must expressly state:

a) That the developer undertakes to return to the purchaser the amounts received on account, including applicable taxes, plus legal interest, if construction is not started or not finished within the agreed periods set in the contract, or if the certificate of habitability, first-occupation licence or equivalent document authorising occupation of the dwelling is not obtained.

b) A reference to the insurance contract or bank guarantee referred to in paragraph One.1.a) of this provision, stating the name of the insurer or guarantor.

c) Designation of the credit institution and the account through which the purchaser must pay the amounts it has undertaken to advance under the contract concluded.

When the contract of sale is executed, the developer, including in the case of communities of owners or cooperatives, shall deliver to the purchaser the document evidencing the guarantee, referred and individualised to the amounts to be advanced on account of the price.

Four. Enforcement of the guarantee.

If construction has not begun or the dwelling has not been delivered, the purchaser may choose between rescinding the contract with return of the amounts paid on account, including applicable taxes, increased by legal interest, or granting the developer an extension, which shall be recorded in an additional clause to the contract, specifying the new period with the date of completion of construction and delivery of the dwelling.

Five. Cancellation of the guarantee.

Once the certificate of habitability, the first-occupation licence or the equivalent document authorising occupation of the dwelling has been issued by the competent administrative body and the developer has evidenced delivery of the dwelling to the purchaser, the guarantees granted by the insurer or guarantor shall be cancelled. Once those conditions are met, the same effect shall occur if the purchaser refuses to take delivery of the dwelling.

Six. Advertising of housing developments.

In the advertising of housing developments with receipt of amounts on account before the start of the works or during the construction period, it shall be compulsory to state that the developer will conduct its activity and contracting in compliance with the requirements established in this Act, expressly naming the guaranteeing insurer or guarantor and the credit institution where the special account into which the advance amounts must be paid is open.

Seven. Infringements and penalties.

Failure to comply with the obligations imposed in this provision constitutes a consumer-protection infringement, to which the general penalty regime on consumer and user protection provided in general legislation and in the corresponding regional rules shall apply, without prejudice to the powers conferred by the rules in force on the Directorate-General for Insurance and Pension Funds.

Failure to comply with the obligation to constitute the guarantee referred to in paragraph One.1 of this provision shall give rise to a penalty of up to 25 per cent of the amounts whose return must be secured, or the penalty applicable under the Autonomous Communities’ own rules.

In addition, the infringements and penalties that may apply under the specific legislation on the regulation of building shall be imposed on the developer, including in the case of communities of owners or cooperatives.

Eight. Implementing regulations.

Regulations may determine the public housing development bodies exempted from the requirements established in this additional provision.

The Government may issue supplementary provisions to implement this additional provision.

What to ask for before paying a deposit off-plan. Under paragraph Three the contract must name the insurer or bank and the special account, and the buyer must be handed a guarantee document individualised to their own payments when the contract is signed. A general certificate that the development is “insured” does not meet that, and nor does paying into the developer’s ordinary account.

Second additional provision. Compulsory nature of the guarantees for material damage caused by flaws and defects of construction

One. The guarantee against material damage referred to in article 19.1.c) of this Act shall be required, from its entry into force, for buildings whose main use is housing.

However, this guarantee shall not be required in the case of an individual self-developer of a single single-family dwelling for own use. Nevertheless, if an inter vivos transfer takes place within the period provided in article 17.1.a), the self-developer shall, unless otherwise agreed, be obliged to take out the guarantee referred to in the preceding paragraph for the time remaining to complete the ten years. For this purpose, public deeds of inter vivos transfer shall not be authorised or registered in the Land Registry unless the constitution of that guarantee is evidenced and attested, unless the self-developer, who must prove that they have used the dwelling, is expressly released by the purchaser from constituting it.

Nor shall that guarantee be required in cases of rehabilitation of buildings intended mainly for housing for whose new-build projects the corresponding building licences were applied for before the entry into force of this Act.

Two. A Royal Decree may make it compulsory to take out the guarantees provided for in paragraphs 1.a) and 1.b) of article 19 for buildings whose main use is housing. A Royal Decree may likewise make it compulsory to take out any of the guarantees provided for in article 19 for buildings intended for any use other than housing.

Buying a villa its owner built. A self-built home sold within ten years needs the ten-year insurance for the remaining years, or an express release signed by the buyer in the deed. A seller may ask for the release; a buyer who gives it gives up the insured route for structural defects and keeps only the claim against the agents and the seller.

Third additional provision. Involvement of the Army Corps of Engineers in the building process in the field of Defence

Members of the Army Corps of Engineers, when taking part in the construction of buildings or installations assigned to Defence, shall be governed, as regards their professional capacity, by Law 17/1999 of 18 May on the Personnel Regime of the Armed Forces and its implementing regulations.

Fourth additional provision. Health and safety coordinator

The qualifying academic and professional degrees for acting as health and safety coordinator in building works, during the preparation of the project and the execution of the works, shall be those of architect, technical architect, engineer or technical engineer, according to their competences and specialities.

Fifth additional provision. Regulation of the right of reversion

(Gives new wording to articles 54 and 55 of the Compulsory Expropriation Act of 16 December 1954, on the former owner’s right to recover expropriated property. Text not reproduced.)

Sixth additional provision. Common infrastructure in buildings for access to telecommunication services

Article 2(a) of Royal Decree-law 1/1998 of 27 February on common infrastructure in buildings for access to telecommunication services shall read as follows:

“a) To all buildings and real-estate complexes in which there is continuity of construction, whether or not residential and whether or not newly built, that are or must be subject to the horizontal property regime regulated by Law 49/1960 of 21 July on Horizontal Property, as amended by Law 8/1999 of 6 April.”

Seventh additional provision. Request that the claim be notified to other agents

A person sued in liability actions based on the obligations arising from their involvement in the building process provided for in this Act may request, within the period granted by the Civil Procedure Act for answering the claim, that the claim be notified to one or more other agents who also took part in that process.

Notification shall be made in accordance with the rules for summoning defendants and shall include an express warning to the other agents called to the proceedings that, if they do not appear, the judgment given shall be binding on and enforceable against them.

Eighth additional provision. Installation of network infrastructure or radio stations in privately owned buildings

Works to install network infrastructure or radio stations in privately owned buildings shall not require a works or building licence or other authorisations, but in any event their developer must file with the authority competent for building works a responsible declaration stating that the works will be carried out according to a project or technical report signed by a competent technician, as appropriate, showing compliance with the applicable requirements of the Technical Building Code. Once the works to install the electronic communications network infrastructure have been executed and finished, the developer must notify the competent authority of the completion of the works and that they have been carried out according to the technical project or technical report.

Ninth additional provision. Compliance with the principle of doing no significant harm to the environment

All interventions on buildings financed from European Union funds or through Spain’s Recovery, Transformation and Resilience Plan must meet, in addition to the provisions of this Act and its implementing rules, the requirements set under those funds in order to respect the principle of doing no significant harm to the environment.

Transitional provisions

First transitional provision

The provisions of this Act, except in matters of compulsory expropriation, which shall be governed by the second transitional provision, shall apply to new-build works and works on existing buildings for whose projects the corresponding building licence is applied for after its entry into force.

Second transitional provision

The fifth additional provision shall not apply to property and rights for which an application for reversion had been filed at the entry into force of the Act.

Third transitional provision. Adaptation to the regime introduced by the first additional provision, “Receipt of amounts on account of the price during construction”, as worded by Law 20/2015 of 14 July on the regulation, supervision and solvency of insurance and reinsurance undertakings

Before 1 July 2016, and for amounts paid on account from that date, insurers must adapt the policies in force on 1 January 2016 to the regime introduced by final provision three.two of Law 20/2015 of 14 July on the regulation, supervision and solvency of insurance and reinsurance undertakings, which amends the first additional provision, “Receipt of amounts on account of the price during construction”, of Law 38/1999 of 5 November on the Regulation of Building.

Repealing provisions

First repealing provision

All provisions of equal or lower rank that conflict with this Act are repealed.

Second repealing provision

Articles 64 to 70 of the Regulation of the Compulsory Expropriation Act, approved by Decree of 26 April 1957, shall remain in force in so far as they do not conflict with or are compatible with the fifth additional provision.

Third repealing provision

All provisions of equal or lower rank that conflict with this Act are repealed, and in particular the following:

a) Law 57/1968 of 27 July on the receipt of advance payments in the construction and sale of dwellings.

b) Decree 3114/1968 of 12 December on the application of Law 57/1968 of 27 July to housing communities and cooperatives.

c) The Order of 29 November 1968 on guarantee insurance for advance payments for dwellings, in so far as it may be in force.

Final provisions

First final provision. Constitutional basis

This Act is issued under the powers vested in the State by the following articles of the Constitution:

a) Article 149.1.6, 8 and 30, as regards the civil and commercial matters of Chapters I and II and the obligations of the building agents and the powers deriving from the exercise of the professions established in Chapter III, without prejudice to the civil, foral or special rights existing in certain Autonomous Communities.

b) Article 149.1.16, 21, 23 and 25, for article 3.

c) Article 149.1.6, 8 and 11, for Chapter IV.

d) Article 149.1.18, for the fifth additional provision.

This Act shall apply without prejudice to the legislative and executive powers assumed by the Autonomous Communities in this field.

Second final provision. Authorisation to the Government to approve a Technical Building Code

The Government is authorised to approve by Royal Decree, within two years of the entry into force of this Act, a Technical Building Code setting the requirements that buildings must meet in relation to the basic requirements established in article 3.1.b) and 1.c).

Until it is approved, the basic building standards (NBE) regulating the technical requirements of buildings, listed below, shall apply to meet these basic requirements:

NBE CT-79 Thermal conditions in buildings.
NBE CA-88 Acoustic conditions in buildings.
NBE AE-88 Actions in building.
NBE FL-90 Load-bearing brick walls.
NBE QB-90 Roofs with bituminous materials.
NBE EA-95 Steel structures in building.
NBE CPI-96 Fire protection conditions in buildings.

The remaining compulsory technical regulations governing any of the basic requirements established in article 3 shall also apply.

Third final provision. Adaptation of the Regulation of the Compulsory Expropriation Act

The Government shall, within six months, adapt section 4 of Chapter IV of Title II of the Regulation of the Compulsory Expropriation Act to the provisions of this Act.

Fourth final provision. Entry into force

This Act shall enter into force six months after its publication in the Official State Gazette, except for its fifth additional provision, second transitional provision, first repealing provision as regards compulsory expropriation legislation, second repealing provision and third final provision, which shall enter into force on the day following that publication.

Where this sits

The previous page translates articles 1 to 16: the basic requirements, the handover of the works from which every period on this page runs, the Building Book and the agents. For defects in a second-hand home, the seller’s own liability for hidden defects runs under the Civil Code; the regional rules for new homes are listed in our Spanish property law index.